GMP Vs Lump Sum Vs Cost Plus: Which Contract Fits Your Build-Out
Three ways to price a build-out, who carries the risk in each, and which fits yours.
- Licensed Texas General Contractor
- Bonded & Insured
- Workers’ Comp Carried
- BBB Accredited A+
- NARI Member
- On Site In All 50 States
- Escrow Services Available
The Direct Answer
Lump sum is a fixed price for a defined scope. Cost-plus pays the contractor's actual costs plus a fee. A guaranteed maximum price (GMP) is cost-plus with a ceiling. For most tenant build-outs with finished drawings, lump sum is the simplest and safest; GMP fits when the scope cannot be fully defined up front.
The Three Side By Side
| Lump Sum | Cost Plus | GMP | |
|---|---|---|---|
| Price | Fixed for the defined scope | Actual cost plus a fee | Actual cost plus a fee, capped |
| Who carries overrun risk | Contractor, within the scope | Owner | Contractor above the cap |
| Who keeps savings | Contractor | Owner | Usually owner, or shared |
| Needs finished drawings | Yes | No | Mostly |
| Transparency into costs | Low | Full | Full |
| Admin for the owner | Low | High | Medium to high |
When Each One Fits
Lump sum.
The drawings are complete, the space has been walked and investigated, and you want one number. The usual choice for a tenant build-out, and what most lenders find easiest to underwrite.
GMP.
The scope is still moving, the building is older and uncertain, or you want the contractor involved before design is finished. You get transparency with a ceiling.
Cost plus.
Emergency work or scope that genuinely cannot be defined. Rare for a build-out, and only with a contractor you trust and an owner who will read every invoice.
What To Read In A GMP Contract
- What counts as cost, and what is in the fee
- The contingency inside the GMP, and who controls it
- How savings under the cap are split
- Which changes raise the cap, and how
- The audit right: can you see the invoices?
How We Price
Most of our work is fixed-price against a defined scope, billed monthly on AIA G702 and G703 against a schedule of values. Cost-plus with a guaranteed maximum price is available where the scope genuinely cannot be defined up front.
FAQ
Is a lump sum contract the same as a stipulated sum?
Does a lump sum mean no change orders?
Next step
You Signed The Lease. Let’s Get It Open.
Send us the space and the brand standards. You’ll get a walkthrough scheduled inside 48 hours and a real number. Not a range, not a “starting at.”
No obligation. No pressure. If we're not the right builder for your project, we'll tell you on the call.
Questions first? Read the build-out FAQ
info@lnbconstruction.net