The Direct Answer

Most franchisees fund a build-out with an SBA 7(a) loan, and some use a 504 where real estate is involved. The lender does not hand over the build-out money at closing. It releases it in draws as work is completed and documented, and the draw paperwork, not the construction, is where franchise openings most often stall.

7(a) Or 504 For A Franchise Build-Out

Both are SBA-guaranteed loans made by a lender. They fit different deals.

SBA 7(a)SBA 504
Typical use in a franchiseLeasehold improvements, equipment, franchise fee, working capitalBuying or building owner-occupied real estate and long-life equipment
Maximum loan$5 millionThe CDC portion is generally capped at $5 million
Leased space build-outThe usual toolRarely, because 504 is built around fixed assets
StructureOne lender, one loanA bank first lien, a CDC second lien and the borrower's equity
EquityLenders commonly require an injection, and start-ups face a minimumTypically 10 percent, more for start-ups or special-purpose buildings

SBA program rules change. Limits and equity requirements here reflect the SOP in force in 2025 and 2026; confirm current terms with your lender before you plan around them.

The Franchise Directory Check

For an SBA loan to a franchisee, the brand has to be eligible, which the SBA tracks through its Franchise Directory. Most established brands are listed. Check yours before you sign a lease that assumes SBA money, because a brand that is not eligible changes the whole financing plan.

How The Money Moves During Construction

  1. Closing.

    The loan closes with the construction budget set aside. The lender wants the signed contract, a line-item schedule of values, the schedule, and the contractor's licence and insurance certificates.

  2. First draw.

    Often covers deposits on long-lead items such as rooftop units and franchisor fixture packages, rather than work in place.

  3. Progress draws.

    Monthly, against a payment application on AIA G702 and G703, with lien waivers and often a site inspection by the lender's inspector.

  4. Final draw.

    Released against the certificate of occupancy, final lien waivers from every tier, and a punch list closed out.

What Stalls A Franchise Draw

  • A lump-sum invoice where the lender expected a schedule of values
  • Missing or wrongly dated lien waivers from a subcontractor or supplier
  • Stored materials billed without proof they are stored and insured
  • Change orders not approved by the lender before they appear on a pay application
  • The inspector's percentage complete disagreeing with the contractor's
  • A franchisor fixture package paid outside the loan with no paper trail

Picking A Contractor For An SBA Job

Ask whether they bill on AIA forms, whether they will sign your lender's contractor agreement, and whether they have run SBA draws before. A contractor who cannot answer all three will cost you weeks at every draw.

FAQ

Can the franchise fee be financed with the build-out?
Often, in a 7(a), subject to the lender's underwriting and SBA rules.
How long does an SBA draw take to fund?
With complete paperwork, commonly one to two weeks from submission, depending on the lender and whether an inspection is required.
Does the franchisor have to approve the contractor?
Many do, and some mandate vendors for fixtures and signage. Check the franchise agreement and the development manual.

Next step

You Signed The Lease. Let’s Get It Open.

Send us the space and the brand standards. You’ll get a walkthrough scheduled inside 48 hours and a real number. Not a range, not a “starting at.”

No obligation. No pressure. If we're not the right builder for your project, we'll tell you on the call.

Questions first? Read the build-out FAQ