Guide
Retainage In Construction: What Owners Should Know
The 5 to 10 percent held back from each payment, and when it should be released.
- Licensed Texas General Contractor
- Bonded & Insured
- Workers’ Comp Carried
- BBB Accredited A+
- NARI Member
- On Site In All 50 States
- Escrow Services Available
The Direct Answer
Retainage is a percentage of each payment, commonly 5 to 10 percent, that the owner holds back until the work is complete and the punch list is closed. It gives the owner leverage to get the last items finished, and it is released at substantial or final completion under the terms of the contract.
How It Works On A Pay Application
A simple example: a $200,000 build-out with 10 percent retainage.
| Line | Amount |
|---|---|
| Work completed to date | $120,000 |
| Retainage held at 10 percent | -$12,000 |
| Earned less retainage | $108,000 |
| Less previous payments | -$72,000 |
| Due this application | $36,000 |
Illustrative figures. Your contract sets the retainage rate, when it steps down and when it is released.
Where It Shows Up
On the AIA G702, retainage is its own set of lines: work completed, materials stored, and the total retained. On the G703 continuation sheet, many contractors show it per line. Either way, the total retained should grow with each draw until it steps down or is released.
Things That Vary By Contract And State
The rate.
5 and 10 percent are common. Some contracts reduce it to 5 percent or zero once the job is half complete.
The release point.
Substantial completion, final completion, or the CO plus the punch list. The contract should say which.
State law.
Many states cap retainage or set deadlines for releasing it, and some treat it differently on private and public work.
Texas lien retainage.
Texas separately requires owners on private projects to retain 10 percent of the contract price for 30 days after completion, to protect against subcontractor lien claims. It is a legal requirement, not just a contract term. Talk to your attorney about how it applies to you.
Before You Release Retainage
- The punch list is closed and signed off
- The CO or final inspection is issued
- Final unconditional lien waivers from the contractor and every subcontractor and supplier
- Closeout documents: warranties, as-builts, manuals
- Your lender and landlord have approved the final draw, if they are funding it
FAQ
Does retainage apply to subcontractors too?
Can retainage be replaced with a bond?
Next step
You Signed The Lease. Let’s Get It Open.
Send us the space and the brand standards. You’ll get a walkthrough scheduled inside 48 hours and a real number. Not a range, not a “starting at.”
No obligation. No pressure. If we're not the right builder for your project, we'll tell you on the call.
Questions first? Read the build-out FAQ
info@lnbconstruction.net