The Direct Answer
A dental office build-out commonly runs $200 to $350 per square foot for construction, before dental equipment. Operatory count drives it more than square footage does, because every operatory needs its own water, drain, air, vacuum, power and data delivered to an exact point, usually through the slab.
What Each Part Of A Practice Costs To Build
Construction only. The chairs, delivery units, imaging and sterilisation equipment are normally bought through your dental supplier and are not in these numbers.
| Area | What Drives The Cost |
|---|---|
| Operatories | Utilities to the chair location, usually in trenches through the slab. Multiplied by the number of ops. |
| Mechanical room | Compressor and vacuum pump, dedicated circuits, ventilation and heat rejection, and sound control. |
| Imaging rooms | Shielding to the physicist's report, which may mean lead-lined drywall or doors. |
| Sterilisation | Sinks, counters and equipment power laid out for a one-way dirty-to-clean flow. |
| Reception and consult | Finishes, millwork and data. The part patients see. |
| Code and accessibility | ADA throughout, and state dental board facility requirements where they apply. |
Planning ranges, not quotes. They assume a mid-cost US market and move a long way with shell condition, jurisdiction and equipment. A walkthrough turns them into a line-item number.
Why Operatory Count Beats Square Footage
Two 2,500 square foot practices can be priced far apart. One has four operatories on a wet wall near the existing plumbing. The other has eight, spread across the floor plate, each needing a trench cut through the slab and patched.
That is why we price dental per operatory. Add or drop an op and a visible line moves, rather than an opaque lump sum.
Second-Generation Dental Space
An existing dental suite can save a great deal, if its utilities land where your operatories go.
When it saves.
Your operatory layout matches the existing stub-outs, the mechanical room is usable, and the imaging room is shielded for your equipment.
When it costs.
Your layout differs, so the old utilities are in the wrong place in the slab and new ones have to be run. You pay for demolition and new work.
How to tell.
Walk it with your equipment vendor's template before you sign. That answers the question in an afternoon.
Budget Lines People Forget
- Dental equipment, usually a separate purchase and often the larger number
- The shielding physicist's report
- IT, imaging software and cabling
- Design and engineering fees
- Permit fees and any state inspection of imaging rooms
- A contingency of 10 to 15 percent
FAQ
Is a DSO rollout priced differently from a single practice?
Should my equipment vendor be involved before construction?
Can I stay open in my old office while the new one is built?
Next step
You Signed The Lease. Let’s Get It Open.
Send us the space and the brand standards. You’ll get a walkthrough scheduled inside 48 hours and a real number. Not a range, not a “starting at.”
No obligation. No pressure. If we're not the right builder for your project, we'll tell you on the call.
Questions first? Read the build-out FAQ
info@lnbconstruction.net