What Is A Change Order In Construction? Process And Tips
A change order is a signed amendment that changes the scope, price or schedule of a construction contract. What goes in one, why they happen on build outs, and how to keep them under control.

A change order in construction is a written, signed amendment to the construction contract that changes the scope of work, the contract price, the schedule, or all three, after the contract is signed. On a commercial build out it is how a tenant, landlord or owner adds, removes or swaps work without starting a new contract, and it is what keeps everyone's numbers honest when plans change mid project.
Change orders are normal. On many tenant improvements, something changes once walls open up or a franchise standard gets updated. What separates a smooth project from a painful one is how those changes are written down, priced and approved.
What a change order includes
- A description of the change: exactly what work is added, removed or modified, tied to the drawings or spec section it affects.
- The cost impact: the amount the contract sum goes up or down, usually with a breakdown of labor, material, subcontractor and markup.
- The time impact: how many days, if any, the schedule moves.
- The new contract totals: the original contract, changes approved so far, this change, and the new contract sum.
- Signatures from the owner or tenant, the contractor and, where there is one, the architect.
On projects that use AIA documents, change orders are commonly written on the AIA G701 form, and every approved change then shows up as its own line on the G702 and G703 pay applications. We explain how that billing works on our AIA billing page.
Why change orders happen on build outs
- Owner or tenant changes: a different finish, an added room, more outlets, a revised layout.
- Hidden conditions: what we find once a ceiling or wall opens up in an older shell, like undersized electrical service or plumbing that is not where the drawings show it.
- Design gaps or errors: something missing or conflicting in the drawings.
- Code or permit comments: changes the city requires during plan review or inspection. See our guide to commercial tenant improvement permitting.
- Brand standard updates: common on franchise projects when the franchisor revises a fixture or finish package. More in franchise build outs and brand standards.
The change order process, step by step
- The change is identified by the owner, architect or contractor.
- The contractor prices it and states any schedule impact.
- The owner reviews, asks questions and approves or rejects.
- Everyone signs before the changed work is done, except in a true emergency.
- The contract sum and schedule are updated, and the change is billed on the next pay application.
How to keep change orders under control
- Finish the design before you sign. Most expensive change orders start as undecided items.
- Walk the space before pricing. A good pre construction walk catches many hidden conditions early.
- Agree on markup and pricing rules up front, in the contract, so every change is priced the same way.
- Never approve work verbally. If it is not written and signed, it is a dispute waiting to happen.
- Keep an owner contingency in your budget, and know how it relates to your tenant improvement allowance.
Change orders and your MEP
A large share of change orders on interior build outs touch mechanical, electrical and plumbing work, because that is what sits behind finished surfaces. If you are not sure what falls under MEP, read what is MEP in construction.
Planning a build out?
LNB Construction is a commercial build out and tenant improvement contractor based in Katy, Texas, working across the Texas metros and on multi location programs nationwide. If you want a clear scope, clear pricing and a written change order process from day one, talk to us about your project.
More From The Jobsite
What Is A Certificate Of Occupancy? Commercial Build Out Guide
A certificate of occupancy (CO) is the document a local building department issues when a space passes its final inspections and can legally be used. Why it matters for a tenant build out and what can hold it up.
What Is A Punch List In Construction?
A punch list is the list of items still to be finished or corrected when a project is substantially complete. Who makes it, what goes on it, and how it ties to retainage and closeout on a commercial build out.
What Is MEP In Construction? Mechanical, Electrical And Plumbing Explained
MEP stands for mechanical, electrical and plumbing: HVAC, power and lighting, water and drains. What each trade covers in a commercial build-out, why MEP drives cost and schedule, and what to ask before you sign a lease.
Next step
You Signed The Lease. Let’s Get It Open.
Send us the space and the brand standards. You’ll get a walkthrough scheduled inside 48 hours and a real number. Not a range, not a “starting at.”
No obligation. No pressure. If we're not the right builder for your project, we'll tell you on the call.
Questions first? Read the build-out FAQ
info@lnbconstruction.net